Tuesday, October 14, 2008

Trailwork on Sunday Oct 19th at 10:30am

We plan to continue work in Section 6. The rock causeway needs to have an entrance and exit put in. We also need to finish up work on the downhill rock armor. Once we get those two projects completed, we plan to start on the uphill rock climbing section just after the causeway.

Meet at the Par 3 lot (parking permit required to park there) and bring water, long pants, maybe bug spray, work gloves, and good work boots/shoes. We will supply the tools.

The more people we get to volunteer, the sooner we can get the first 1/2 of Section 6 finished and open for riding.